Cost per part, not cost per kilo: the sheet-to-part maths

Material price is one line in the cost of a plastic part. Yield, machining time, tool life and scrap decide. How to run the sheet-to-part numbers.

Delivery
POM-C Natural Sheet and Rod

Cost per part plastic analysis is where most machining budgets are won or lost, yet the quotation a buyer receives usually shows only the material price per kilo. That single figure hides yield, machining time, tool life, scrap and downtime, and it is the least useful number when comparing two materials or two suppliers. A part that costs more per kilo can easily cost less per finished piece once the whole sheet-to-part flow is counted.

This article walks through the terms that make up the real cost of a machined plastic part and shows how a worked comparison of POM against PEEK is built up on one component. The method is the same whether you machine in-house or buy finished parts, and it uses the full materials range we hold as stock.

Why cost per kilo misleads

Price per kilo is a convenient unit because it is easy to quote and easy to compare, but it measures the wrong thing. You do not buy a kilo of plastic; you buy a finished part, and the material you pay for includes everything turned into swarf and every offcut that never becomes a part. Two grades can differ by a factor of ten on price per kilo and by much less on cost per part, or the reverse, depending on how much material each one needs and how long each one takes to machine. The only honest comparison is a cost per part plastic calculation that puts the same part, the same drawing and the same batch size against each option, and then divides total cost by the number of good parts shipped.

Cost term What it includes Typical weight
Material buy price Sheet or rod at the quoted price per kilo Often quoted, rarely decisive alone
Yield Offcuts, nesting and reusable swarf Can exceed the price gap between grades
Machining time Cycle time on the machine Usually the largest term after material
Tool life Cutters consumed per part Significant in glass-filled grades
Scrap and rework Rejects and second operations Small percentages, large money
Downtime and replacement Line stops and labour to change the part Decides the cheapest option overall

Yield: nesting, offcuts and what you actually pay for

Yield is the share of the material you buy that ends up in the finished part. It depends on the size of the stock shape, the way parts are nested on a sheet, and the number of parts per blank. A part that fits three across a standard sheet can have a very different yield from the same part nested four across with a different edge allowance, and that difference is often larger than the price gap between two suppliers. Offcuts that are large enough to be reused should be counted as recovered material rather than as scrap, and the cutting plan should be designed with reuse in mind. In our experience, a careful nesting exercise on a high-value grade such as PEEK can change the cost per part more than any negotiation on the resin price, and the same stock shape range is available cut to the blank sizes a nesting plan calls for.

PEEK natural sheet and rod stock shapes. PEEK sheet utilised across a cutting plan

Machining time and tool life by material

Machining time is usually the largest single term after material, and it varies between grades more than buyers expect. Soft, unfilled plastics such as UHMW-PE cut fast but can be difficult to hold to a tolerance; filled and glass-filled grades are stiffer but abrasive, so tool life drops and feeds and speeds have to come down. Hard, high-temperature grades such as PEEK and PEI machine slowly and demand rigid setups to avoid chatter and scrap. Tool life belongs in the calculation because a grade that wears cutters quickly adds cost with every part, not just at the end of the run. The right comparison is cycle time plus tooling cost per part, measured on the same machine and the same programme. If the blanks are supplied close to size by a cut-to-size service, the first roughing passes can disappear altogether.

Scrap and rework rates in plastics

Scrap is where the price per kilo illusion breaks down most visibly. Plastics are more sensitive than metals to clamping pressure, heat build-up and residual stress, so the same workpiece can come out usable in one setup and cracked, warped or dimensionally out in the next. A grade that is cheaper per kilo but produces more rework or rejects can cost more per good part than a grade that machines cleanly. It is worth tracking the reject rate by grade and by operation, because a small change in scrap percentage often outweighs a large change in material price. Rework is the hidden version of the same problem: a part that has to be re-cut ties up the machine twice and delays the whole order.

POM-C natural acetal sheet and rod. Acetal sheet nesting for machined parts

Downtime and replacement frequency

The last term sits outside the machine shop altogether. A lower-cost part that fails early and stops a line can cost far more than the price difference on the whole order, and this is where total cost of ownership rather than purchase price decides. Running temperature, chemical exposure, wear rate and creep all set the replacement interval, and a more expensive grade can be the cheaper choice simply because it lasts longer. When we compare two options with a customer, we look at expected life, the cost of a line stop and the labour to change the part, not just the invoice for the sheet. That is the framing that keeps a cost per part plastic decision defensible to a finance team, and we set out a POM and PEEK comparison in our cost comparison notes.

Questions buyers ask about cost per part in plastics

Why is cost per kilo a poor way to compare plastics?

Because you do not buy the kilo, you buy the part. Price per kilo ignores yield, machining time, tool life and scrap, all of which differ between grades. Two materials can rank one way on price per kilo and the opposite way on cost per good part, so the comparison has to be made on the finished piece.

How do I calculate the yield of a plastic part?

Work out the volume of material in the finished part and divide it by the volume of stock consumed, including the blank and its edge allowance. Then decide whether the offcuts can be reused. A nesting change that lifts yield by ten per cent usually beats a ten per cent discount on the sheet.

Is PEEK always more expensive per part than POM?

Per kilo, yes by a wide margin. Per part it depends on the duty. If the part is small, runs cool and does not need PEEK’s temperature or wear resistance, POM wins clearly. If PEEK lasts several times longer in a hot or abrasive position, the cost per part can cross over in its favour.

How should replacement frequency enter the cost?

Convert the expected life into a cost per operating hour, then add the labour and the cost of a line stop each time the part is changed. A part that costs twice as much but lasts five times longer is the cheaper option once downtime is included. Ask us through the contact page if you want help running the numbers.

Need a material recommendation?

Send us the application and we will reply with two or three candidate grades and a price.

Ask an engineer
Share this article