An RFQ that says “ESD sheet, 10 mm, please quote” gets a fast answer and a slow project. The supplier guesses the grade, quotes the cheapest carbon sheet in the drawer, and the divergence appears weeks later — at incoming inspection, in the fixture, or at the customer audit. The fix is not a longer document; it is five well-chosen lines. With these five, a quotation either matches or visibly fails to match, and both outcomes are useful. Here is what each line needs to say.

Line 1: material and ESD type

Name the polymer family and the electrical class: “carbon-filled ESD POM, dissipative” or “conductive PEI, dissipative band”. This single line eliminates the most common wrong delivery — a material that is ESD, but not the family the fixture was designed around. If you have a brand reference (SEMITRON ESd M7, DELRIN-type acetal), add it marked as reference only; the family and class are the binding part. The ESD type matters as much as the family: dissipative and conductive grades of the same resin sit decades apart, and substituting one for the other is not a price decision.

Line 2: the two resistivity bands, with a standard

Write surface resistivity and volume resistivity as ranges, each with the measurement standard: “surface 10^6 – 10^9 ohms and volume below 10^8 ohm-cm per ASTM D257, at 23 °C / 50% RH after 48 h conditioning”. Citing the standard is what makes the number enforceable; a bare “dissipative” is unquotable because every supplier fills it with its own decade. If your process runs dry — winter halls, desiccated cleanrooms below 30% RH — add the working humidity as a second condition, because the 50% RH figure will not follow the sheet onto your line. If your program runs on decay time, cite the decay target instead of or in addition to resistivity: “under 2 s from 1000 V to 100 V per ANSI/ESD STM11.31”.

Line 3: dimensions and tolerances

Thickness, sheet or cut-to-size dimensions, and the tolerances that actually matter to the fixture. For cut blanks, tolerance on length and width and a thickness tolerance are usually enough. For plates that must sit flat, add flatness — this is the line that saves reflow-adjacent and large-format parts: “flatness 0.5 mm over 1000 mm”. Uncited thickness defaults to the extrusion standard tolerance, which on some lines is generous enough to matter in a pocket-milled fixture. Machined parts are quoted from drawings, but the blank specification still needs these lines so the supplier cuts stock that will survive the machining plan.

Line 4: surface condition and cleaning

State the surface you expect to receive and the cleaning the material must survive. “Peel film both sides, no surface defects” is a legitimate line for optical-facing parts. For parts that will be washed in service, name the solvent: “resistivity to be maintained after repeated cleaning with IPA” — this single clause excludes migratory antistatic grades that would fail silently after the third wash. If the part is machined and the exposed core matters, the line also carries the volume resistivity requirement from Line 2, because a machined pocket tests the bulk, not the film.

Line 5: certification

What paperwork must travel with the sheet: “mill certificate with surface and volume resistivity values per lot” is the standard ask; add material origin, date code and, for regulated environments, RoHS/reach conformity. For a first article, ask for a test report on your own specified conditions, not just the supplier’s standard condition. This line costs the supplier a few minutes per lot and costs you nothing — and it is the difference between an audit conversation with numbers in hand and one without.

The five lines as a template

Line What it states Example wording
1. Material Polymer family + ESD class Carbon-filled ESD POM, dissipative (reference: ESd M7)
2. Resistivity Surface + volume ranges, standard, humidity 10^6 – 10^9 ohms surface, < 10^8 ohm-cm volume, ASTM D257, 23 °C / 50% RH, 48 h
3. Dimensions Thickness, size, tolerances, flatness 10 mm +0.3/-0.1, cut 500 x 1000 ±1 mm, flatness 0.5 mm over 1000 mm
4. Surface / cleaning Surface condition, solvent survival Masked both sides; resistivity maintained after IPA cleaning
5. Certification Mill certificate, lot values, conformity Certificate per lot with resistivity values; RoHS conformity

What these five lines change in practice

Quotations become comparable: three suppliers answering the same five lines are answering the same material, not three approximations of it. Incoming inspection has a contract to test against. And the audit trail exists before the first part is machined, not after the auditor asks. Suppliers benefit too — a five-line RFQ is quoted faster and more accurately than a vague one, and at our desk it usually moves straight to the material that the process actually needs, with the two rungs either side quoted for comparison.

Short answers

Do I need all five for a simple tray?Lines 1 to 3, yes. Line 4 matters the moment washing is involved; line 5 the moment an audit is possible. A tray for internal use can run on three lines.

Which line gets forgotten most?Line 3’s flatness, and Line 2’s humidity condition. Both are invisible until the part is on the line.

Can the five lines be one paragraph?Yes — the form does not matter; the content does. One dense paragraph beats a three-page RFQ that misses the resistivity standard.

Need a material recommendation?

Send us the application and we will reply with two or three candidate grades and a price.

Ask an engineer